Hamburger Hungária Power Plant
The Hamburger Hungária power plant was constructed between 25 March 2014 and 30 June 2015. Besides the multi-fuel facility, storage areas were built as well. During the project our company mainly delivered the following product types:
- CKT-4: 2 500 m3
- C30/37-XC4-24-F2: 6 000 m3
- CP4/2,7 : 1 500 m3
One of the major challenges for the engineers was the fact that they only had 2 days to create the 2 000 m3 foundation. The task needed special cement and the 1.5 m thick concreting warranted constant supervision.